Ayia Napa Marina’s Construction Progress Update

Ayia Napa Marina’s construction proceeded extremely fast during July, despite the intense heat.

Significant work has been completed regarding the buildings of the development. Specifically, all 135 piles supporting the East Tower have been placed, setting the foundations for the superstructure that will follow. Works have been progressing on the maintenance, chandlery and administration buildings as well.

With the dredging complete and reclamation very close to completion, works on the island have commenced and are proceeding quickly. The island’s blockwall is at 44 percent, making it visible and shaping it day by day. Precast concrete elements are at about 73 percent average production completion, speeding up the construction of the South Breakwater.